Connect with us

News

Power Outage In Osogbo Is For Safety- IBEDC

Published

on

…….Promises To Restore Power In four Weeks

The management of Ibadan Electricity Distribution Company, IBEDC, has disclosed that the current power outage in some communities in Osogbo, capital of Osun State is geared towards the protection of lives and property.

IBEDC

The affected communities include; Iludun, Kasmo, Fiwasaye, Oluode/Kolawole, Owode/Igbona, Surulere/Oke Ayo/Sabo, Atelewo/Plantation, Arikalamu, Akintokun, Ifesowapo, Ife Olu, Asoje, Mosadoluwa, Isokan and Kelebe in Osogbo and Ikirun under the Oluode 11KV and Ipetu ile 11KV feeders.

In a statement signed by the state Regional Communication Officer, Kikelomo Owoeye, the organization apologized to its customers and promised to restore power in four weeks.

According to the release, “The management of Ibadan Electricity Distribution Company hereby wishes to inform and apologize to its esteemed customers that the current power outage being experienced is due to critical safety issues that have arisen on the power lines servicing these areas. This has led to several wire cuts and snaps which if unattended to can lead to electrocution of unsuspecting individuals, loss of lives and property.

“IBEDC being a customer-oriented organization, deliberately shut down the feeder supplying power to these areas after due consultation with the community leaders, without minding the revenue loss that would result from this to enable the company thoroughly and effectively carry out urgent repairs on the affected lines.

“As part of its responsibility to customers, the company engaged the community leaders and members serviced by the feeder to explain the cause of the outage whilst proposing a temporary solution that would ensure some supply, pending the completion of the repair work which is an extremely intensive and costly exercise.

“From one of the many engagements prior to the protest, a four-person committee made of the community representatives was delegated to work with the distribution company’s technical team to conclude on load-shedding plans in order not to put the communities in total blackout pending the time the project is embarked upon. Unfortunately, the leaders reported back that some of the community members are not in support of the load-shedding proposal which happens to be the only temporary solution.

“IBEDC sincerely apologises to its esteemed customers in these communities for the inconvenience and appeal to them to bear with the palliative actions they have proposed for rationing power supply during the period of repairs.

IBEDC however  implored customers to desist from the current spate of protests and threats embarked upon by some set of people in the areas as it would not remedy the situation, but may lead to an exacerbation of the issue and in turn, slow the progress of repairs.

“IBEDC is fully committed to the rehabilitation of this line within the next four weeks, and has promised to restore power to all the affected communities in time.” the release reads in part.

Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Trending